Good progress is being made on the building project at the Sioux Central School in Sioux Rapids.

Principal Jeff Scharn says the contractor should have the football field turf completed by the end of this week… with work to begin on the bleachers and concession stand, followed by installation of the all-weather track. Scharn says the outside athletic facilities should be completed by this fall… and the contractor is also working on getting everything enclosed before winter.

The project includes a football/track complex on the north side of the school… a new elementary gymnasium, locker room renovations and addition, and adding a multi-purpose/ wrestling room on the northwest side of the school… and on the southeast corner, construction of special education classrooms. The roof on the present building will also be replaced.